Rain on Friday, May 6, 2022 prevented the paving of the street gutter in front of the library. This will be done next week.
The sidewalk and parking will be accessible over the weekend – please visit the restaurants and shops of SoBro this weekend!
Vault work at 73 S. Broadway has been completed, no further work scheduled there until the sidewalk gets poured.
Monday, 5/9, A-Tech will begin excavation of the curb from Hudson Avenue to Maura’s Restaurant.
Monday, 5/9, A-Tech will begin work on the vault in front of Pizza Bistro. Access will be maintained to the businesses.
Once curb is excavated, work can begin on excavating sidewalk (takes about a week and a half) and then moving on to new sidewalk cement, followed by paving the street gutter line.
The full process of the new sidewalk construction can take a couple of weeks, and can be impacted by weather and cement suppliers.
In the meantime, work will progress in the vaults on the west side of S. Broadway, one by one.
Village staff is meeting with contractors and inspectors daily for updates and conducts a full project review every other week.
This update is published on the village website. Follow the project here.